Overview
Modular storage supporting construction power for Shenzhen's rail-transit build-out — a 2.5 MW / 10 MWh system that broke ground in May 2026 and completed its 10kV high-voltage grid connection in June, built and commissioned within a single month. Operating under Guangdong's time-of-use industrial tariff, it runs on peak-valley arbitrage, cycling roughly 9,000 kWh a day and avoiding an estimated 1,600 t of CO₂ annually — a green-power benchmark for rail-transit infrastructure.
2.5 MW / 10 MWh · ~1,600 t CO₂ avoided/yr
Data sheet
- Capacity
- 2.5 MW / 10 MWh
- Grid connection
- 10kV 高压并网 / 10kV high-voltage
- Build time
- 1 个月(2026.5–6)/ 1 month (May–Jun 2026)